Question: table [ [ Activity , Duration ( days ) , Predecessors ] , [ A , 5 , None ] , [ B ,

\table[[Activity,Duration (days),Predecessors],[A,5,None],[B,3,A],[C,8,A],[D,6,B],[E,4,B, C],[F,2,C],[G,7,D, E],[H,3,E],[I,4,F],[J,6,H, I]]
2.1. Construct a network diagram.
2.2. Determine ES, EF, LS, LF, Slack.
2.3. Determine the critical path and project completion time.
2.4. If you need to reduce the project duration by 4 days, identify which activities
 \table[[Activity,Duration (days),Predecessors],[A,5,None],[B,3,A],[C,8,A],[D,6,B],[E,4,B, C],[F,2,C],[G,7,D, E],[H,3,E],[I,4,F],[J,6,H, I]] 2.1. Construct a network diagram. 2.2.