Question: table [ [ Activity , Duration,ES , EF , LS , LF , Slack ] , [ A , 0 , 3 , ,
tableActivityDuration,ESEFLSLFSlackABCDEFGH
Time left ::
A Complete the table for Duration and slack marks
B Identify the critical Activities, critical path and the duration of the project. marks
C If the variation on the project is weeks. What would be the probability of completing the project in two weeks more than, two weeks less than and on the project Duration. marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
