Question: table [ [ Activity , Duration,ES , EF , LS , LF , Slack ] , [ A , 0 , 3 , ,

\table[[Activity,Duration,ES,EF,LS,LF,Slack],[A,0,3,,3,0,],[B,3,8,5,10,,],[C,3,10,3,10,,],[D,10,13,10,13,,],[E,,,13,12,17,4],[F,,13,17,13,17,],[G,,10,12,15,17,],[H,5,17,22,17,22,]]
Time left 2:02:32
A. Complete the table for Duration and slack (13 marks).
B. Identify the critical Activities, critical path and the duration of the project. (4+2+1 marks).
C. If the variation on the project is 4 weeks. What would be the probability of completing the project in two weeks more than, two weeks less than and on the project Duration. marks
 \table[[Activity,Duration,ES,EF,LS,LF,Slack],[A,0,3,,3,0,],[B,3,8,5,10,,],[C,3,10,3,10,,],[D,10,13,10,13,,],[E,,,13,12,17,4],[F,,13,17,13,17,],[G,,10,12,15,17,],[H,5,17,22,17,22,]] Time left 2:02:32 A. Complete the table for Duration and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!