Question: table [ [ Activity , Immediate Predecessor ( s ) , T e , VAR,Slack ] , [ A , - , 5 ,

\table[[Activity,Immediate Predecessor(s),Te,VAR,Slack],[A,-,5,0.444,0],[B,-,2,0.111,4],[C,-,3,0.444,6.5],[D,A,7.5,0.25,0],[E,B,6.5,0.694,4],[F,C,8,0.111,6.5],[G,D, E,5,0.111,0]]
What is the critical path for the project described by this table?
A.C-F
B.A-B-C
C.B-E-G
D.A-D-G
 \table[[Activity,Immediate Predecessor(s),Te,VAR,Slack],[A,-,5,0.444,0],[B,-,2,0.111,4],[C,-,3,0.444,6.5],[D,A,7.5,0.25,0],[E,B,6.5,0.694,4],[F,C,8,0.111,6.5],[G,D, E,5,0.111,0]] What is the critical path for the project