Question: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [ TIME ] , [ ( WEEKS ) ] ] ] , [ A

\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,2],[B,A,5],[C,A,4],[D,B,3],[E,C%media:cm.png%,4],[F,D,1],[G,D,1],[H,F,2],[,E%media:cm.png%,]]
b. What is the critical path?
A-C-E-F-G-H
A-B-D-E-H
A-C-E-G-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack and how much?
B,1 week; H,3 weeks; F,2 weeks
C,4 weeks; F,2 weeks; G,2 weeks
B,3 weeks; C,1 week; F,4 weeks
 \table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,2],[B,A,5],[C,A,4],[D,B,3],[E,C%media:cm.png%,4],[F,D,1],[G,D,1],[H,F,2],[,E%media:cm.png%,]] b. What is the critical path? A-C-E-F-G-H A-B-D-E-H A-C-E-G-H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!