Question: The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the

The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No activity can be crashed more than two weeks.

CRASHING COSTS
Activity Immediate Predecessor Normal Time (weeks) First Week Second Week
A 12 $15,000 $20,000
B A 14 10,000 10,000
C 10 5,000 5,000
D C 17 20,000 21,000
E C 18 16,000 18,000
F C 12 12,000 15,000
G D 15 24,000 24,000
H E 8
I F 7 30,000
J I 12 25,000 25,000
K B 9 10,000 10,000
M G 3
N H 11 40,000
P H, J 8 20,000 20,000
End K, M, N, P

Crash schedule: (1 week each)

week 1

1)P

2)C

3)E

4)F

week 2

1)F

2)E and P

3)P

4)E

week 3

1)E and P

2)C

3)P

4)E

week 4

1)F

2)P

3)C

4)E

week 5

1)E

2)E and P

3)P

4)F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!