Question: The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No activity can be crashed more than two weeks.
| CRASHING COSTS | |||||
| Activity | Immediate Predecessor | Normal Time (weeks) | First Week | Second Week | |
| A | 12 | $15,000 | $20,000 | ||
| B | A | 14 | 10,000 | 10,000 | |
| C | 10 | 5,000 | 5,000 | ||
| D | C | 17 | 20,000 | 21,000 | |
| E | C | 18 | 16,000 | 18,000 | |
| F | C | 12 | 12,000 | 15,000 | |
| G | D | 15 | 24,000 | 24,000 | |
| H | E | 8 | |||
| I | F | 7 | 30,000 | ||
| J | I | 12 | 25,000 | 25,000 | |
| K | B | 9 | 10,000 | 10,000 | |
| M | G | 3 | |||
| N | H | 11 | 40,000 | ||
| P | H, J | 8 | 20,000 | 20,000 | |
| End | K, M, N, P | ||||
Crash schedule: (1 week each)
week 1
1)P
2)C
3)E
4)F
week 2
1)F
2)E and P
3)P
4)E
week 3
1)E and P
2)C
3)P
4)E
week 4
1)F
2)P
3)C
4)E
week 5
1)E
2)E and P
3)P
4)F