Question: table [ [ Activity , Immediate Predecessor,Time ( weeks ) ] , [ A , None, 6 ] , [ B , A ,

\table[[Activity,Immediate Predecessor,Time (weeks)],[A,None,6],[B,A,4],[C,A,7],[D,C,2],[E,B, D,4],[F,D,3],[G,E, F,7]]
a) Draw network diagram.
b) How many possible paths are there in the project?
c) Which path is the critical path?
d) How many weeks of slack does activity B?
e) How many weeks of slack does activity C?
 \table[[Activity,Immediate Predecessor,Time (weeks)],[A,None,6],[B,A,4],[C,A,7],[D,C,2],[E,B, D,4],[F,D,3],[G,E, F,7]] a) Draw network diagram. b) How