Question: table [ [ Activity , Immediate Predecessor,Time ( weeks ) ] , [ A , None, 6 ] , [ B , A ,
tableActivityImmediate Predecessor,Time weeksANone,BACADCEB DFDGE F
a Draw network diagram.
b How many possible paths are there in the project?
c Which path is the critical path?
d How many weeks of slack does activity B
e How many weeks of slack does activity C