Question: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 7 ] , [ B , A

\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,7],[B,A,4],[C,A,8],[D,C,5],[E,B%media:cm.png% D,3],[F,D,6],[G,E&media:cm.png% F,3]]
a. What is the critical path?
A-C-D-F-G
A-B-E-G
A-C-D-E-G
A-B-D-F-G
b. How many weeks will it take to complete the project?
Answer is complete and correct.