Use the information contained below to compress one time unit per move using the least cost method.
Question:
Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project? What is the cost?
Note: The correct normal project duration and total direct cost are provided.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management The Managerial Process
ISBN: 978-1259666094
7th edition
Authors: Erik W. Larson, Clifford F. Gray
Question Posted: