Question: table [ [ Activity , LS , LF ] , [ H , 1 5 , 2 2 ] , [ G , 1

\table[[Activity,LS,LF],[H,15,22],[G,12,22],[F,9,15],[E,8,12],[D,14,15],[C,10,12],[B,0,8],[A,3,10]]
The slack times are:
\table[[Activity,Slack],[A,3],[B,0],[C,3],[D,7],[E,0],[F,1],[G,0],[H,1]]
The activities on the critical path are
The total project completion time for Dave = weeks.
 \table[[Activity,LS,LF],[H,15,22],[G,12,22],[F,9,15],[E,8,12],[D,14,15],[C,10,12],[B,0,8],[A,3,10]] The slack times are: \table[[Activity,Slack],[A,3],[B,0],[C,3],[D,7],[E,0],[F,1],[G,0],[H,1]] The activities on the critical