Question: table [ [ Activity , Preceding activity,Duration ( hours ) ] , [ A , - , 5 ] , [ B , -

\table[[Activity,Preceding activity,Duration (hours)],[A,-,5],[B,-,14],[C,A, B,17],[D,C,7],[E,C,14],[F,D,6],[G,F,3],[H,E,9]]
(a) Construct the network diagram for the project.
(b) Identify the critical path.
(c) Calculate the expected completion time for the project.
(a) The network diagram for the project is
 \table[[Activity,Preceding activity,Duration (hours)],[A,-,5],[B,-,14],[C,A, B,17],[D,C,7],[E,C,14],[F,D,6],[G,F,3],[H,E,9]] (a) Construct the network diagram for the