Question: table [ [ Activity , Predecessor, table [ [ Estimate ] , [ in weeks ] ] ] , [ Start , -

\table[[Activity,Predecessor,\table[[Estimate],[in weeks]]],[Start,-,0],[C,Start,6],[B,Start,4],[P,Start,3],[A,C, B, P,7],[U,P,4],[T,A,2],[R,A,3],[N,U,6],[End,T, R, N,0]]
*Source citation: RMC Project Management, Inc. (2013)
What is the duration of the critical path?
7 weeks
18 weeks
16 weeks
15 weeks
\ table [ [ Activity , Predecessor, \ table [ [