Question: table [ [ Activity , Predecessor,Optimistic,Most Likely,Pessimistic ] , [ A , - , 1 2 , 1 6 , 2 5 ] ,

\table[[Activity,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,12,16,25],[B,-,7,14,22],[C,-,5,10,14],[D,A,15,18,25],[E,C,8,12,18],[F,B,9,12,15],[G,F,18,22,29],[H,D,E,G,15,19,27]]
Using Table 7.13, what is the expected time of completion of the project?
 \table[[Activity,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,12,16,25],[B,-,7,14,22],[C,-,5,10,14],[D,A,15,18,25],[E,C,8,12,18],[F,B,9,12,15],[G,F,18,22,29],[H,D,E,G,15,19,27]] Using Table 7.13, what is the expected time of