Question: table [ [ Activity , Predecessor,Time ( weeks ) ] , [ A , - - , 6 ] , [ B , -

\table[[Activity,Predecessor,Time(weeks)],[A,--,6],[B,--,6],[C,A,4],[D,B,9],[E,C,D,11],[F,E,3]]
Using Table 7.4, what is the early finish time for activity E? week 14
week 21
week 25
week 17
 \table[[Activity,Predecessor,Time(weeks)],[A,--,6],[B,--,6],[C,A,4],[D,B,9],[E,C,D,11],[F,E,3]] Using Table 7.4, what is the early finish time for