Question: table [ [ ACTIVITY , table [ [ IMMEDIATE ] , [ PREDECESSOR ( S ) ] ] , TIME ESTIMATES ( IN
tableACTIVITYtableIMMEDIATEPREDECESSORSTIME ESTIMATES IN WEEKSOPTIMISTICtableMOSTLIKELYPESSIUISTicABACADAEBFGFF
a What is the expected estimated time for activity
b What is the variance for activity C
c Based on the calculation of estimated times, what is the critical path?
d What is the estimated time of the critical path?
e What is the activity variance along the critical path?
f What is the probability of completion of the project before week
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
