Question: table [ [ Activity , table [ [ Predecesso ] , [ r ( s ) ] ] , table [ [

\table[[Activity,\table[[Predecesso],[r(s)]],\table[[Time],[(weeks)]]],[A,--,3],[B,--,4],[C,--,2],[,,],[D,A,4],[E,A, B,5],[F,A, B, C,2],[,,],[G,D, E,1],[H,E,6],[I,E, F,2],[,,],[J,G, H, I,4],[K,H, I,3],[L,I,6]]
Using Table 7.6, what is thetcritical path for this project?
Select one:
A. B-E-H-J
B.B-E-H-K
 \table[[Activity,\table[[Predecesso],[r(s)]],\table[[Time],[(weeks)]]],[A,--,3],[B,--,4],[C,--,2],[,,],[D,A,4],[E,A, B,5],[F,A, B, C,2],[,,],[G,D, E,1],[H,E,6],[I,E, F,2],[,,],[J,G, H, I,4],[K,H, I,3],[L,I,6]] Using Table