Question: table [ [ Activity , table [ [ Normal ] , [ Time ] ] , table [ [ Minimum ] ,

\table[[Activity,\table[[Normal],[Time]],\table[[Minimum],[Time]],\table[[Crash Cost],[per Week]]],[A,8,7,200],[B,5,3,250],[C,5,3,1750],[D,6,5,500],[E,8,5,1500],[F,4,3,1200],[G,6,5,1000],[H,4,2,2000]]
PART 1- CRITICAL PATHS
Find the duration of each of the possible paths.
ACEFH -
ADEFH -
ACEGH -
ADEGH -
BDEFH -
BDEGH -
What is the Critical Path? What is the duration of this project presently?
What would be the penalty associated for the project in the current state?
 \table[[Activity,\table[[Normal],[Time]],\table[[Minimum],[Time]],\table[[Crash Cost],[per Week]]],[A,8,7,200],[B,5,3,250],[C,5,3,1750],[D,6,5,500],[E,8,5,1500],[F,4,3,1200],[G,6,5,1000],[H,4,2,2000]] PART 1- CRITICAL PATHS Find the duration of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!