Question: table [ [ Activity , table [ [ Normal ] , [ Time ] ] , table [ [ Minimum ] ,
tableActivitytableNormalTimetableMinimumTimetableCrash Costper WeekABCDEFGH
PART CRITICAL PATHS
Find the duration of each of the possible paths.
ACEFH
ADEFH
ACEGH
ADEGH
BDEFH
BDEGH
What is the Critical Path? What is the duration of this project presently?
What would be the penalty associated for the project in the current state?