Question: table [ [ Activity , table [ [ Predecess ] , [ or ] ] , table [ [ Time ( we

\table[[Activity,\table[[Predecess],[or]],\table[[Time(we],[s)]]],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]]
Using Table 7.4, what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?
Select one:
A. three activities
B. two activities
C. four or more activities
D. one activity
 \table[[Activity,\table[[Predecess],[or]],\table[[Time(we],[s)]]],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]] Using Table 7.4, what is the minimum number