Question: table [ [ Activity , table [ [ Predecess ] , [ or ] ] , table [ [ Time ( we
tableActivitytablePredecessortableTimewesABACDCEAFBGD E F
Using Table what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?
Select one:
A three activities
B two activities
C four or more activities
D one activity