Question: table [ [ Activity , table [ [ Immediate ] , [ Predecessor ] ] , Optimistic, table [ [ Most ]

\table[[Activity,\table[[Immediate],[Predecessor]],Optimistic,\table[[Most],[Likely]],Pessimistic,Sigma,Variance],[A,-,2,3,4,0.333,0.111],[B,-,2,5,8,1,1],[C,A,1,2,9,1.33,1.78],[D,A,5,5,5,0,0],[E,B, C,6,7,8,0.333,0.111],[F,B,14,14,14,0,0],[G,D,E,1,5,9,1.333,1.78],[H,G,F,1,4,8,1.167,1.361]]
What is the variance of the critical path?
a.5.222
b.4.364
c.5.144
d.1.361
e.2.361
 \table[[Activity,\table[[Immediate],[Predecessor]],Optimistic,\table[[Most],[Likely]],Pessimistic,Sigma,Variance],[A,-,2,3,4,0.333,0.111],[B,-,2,5,8,1,1],[C,A,1,2,9,1.33,1.78],[D,A,5,5,5,0,0],[E,B, C,6,7,8,0.333,0.111],[F,B,14,14,14,0,0],[G,D,E,1,5,9,1.333,1.78],[H,G,F,1,4,8,1.167,1.361]] What is the variance of the critical path? a.5.222

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!