Question: table [ [ Activity , table [ [ Tormal ] , [ ( weeks ) ] ] , table [ [ Crash
tableActivitytableTormalweekstableCrashTimeweekstableCost to Crash$ per weektableImmediatePredecessorsANoneBNoneCADAEBFC DGD EHFIG
The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table Indirect project costs amount to $ per day. The company will incur a $ per