Question: table [ [ Activity , table [ [ Duration ] , [ ( Days ) ] ] , table [ [ Immediate

\table[[Activity,\table[[Duration],[(Days)]],\table[[Immediate Predecessor],[Activities]]],[A,2,-],[B,3,-],[C,4,A],[D,5,A & B],[E,8,C & D],[F,3,D],[G,2,F],[H,3,G]] Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for each activity, and highlight the critical path indicating the length of this project. Please provide formula also on how to calculate es , ef, ls, and lf
 \table[[Activity,\table[[Duration],[(Days)]],\table[[Immediate Predecessor],[Activities]]],[A,2,-],[B,3,-],[C,4,A],[D,5,A & B],[E,8,C & D],[F,3,D],[G,2,F],[H,3,G]] Using the following information, create