Question: The following activities are required for completing a project: a. Draw a network diagram of this project showing the activities and their expected duration times.
The following activities are required for completing a project:

a. Draw a network diagram of this project showing the activities and their expected duration times.
b. What is the critical path and the expected completion time of the project?
c. What is the probability of completing the project in 41 days or less?
Activity Duration, Days Activity Immediate Predecessor Optimistic Most Likely Pessimistic 14 12 19 28 H,I