Question: table [ [ Activity , Time ( weeks ) , Immediate Predecessor ( s ) , Activity,Time ( weeks ) , Immediate Predecessor (

\table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (weeks),Immediate Predecessor(s)],[A,6,-,E,4,B],[B,6,-,F,7,B],[C,3,A,G,9,C, E],[D,1,A,H,7,D , F]]
Dave's earliest start (ES) and earliest finish (EF) are:
Dave's latest start (LS) and latest finish (LF) are:
The slack times are:
The activities on the critical path are
The total project completion time for Dave =20 weeks.