Question: table [ [ , Activity,Predecessors,Optimistic,Most Likely,Pessimistic ] , [ table [ [ les ] , [ nments ] ] ] , [ ,

\table[[,Activity,Predecessors,Optimistic,Most Likely,Pessimistic],[\table[[les],[nments]]],[,B,,2,4,6],[,C,A, B,3,4,8],[e Questionnaire,D,C,2,3,7],[E,D,4,6,8],[F,E,5,8,13],[G,E,4,4,4],[H,F, G,2,4,6],[What is the expected duration of the non-critical path BCDEGH?],[17,,,,],[25.25,,,,],[O 26,,,,],[O 37.33,,,,],[34.33,,,,]]
 \table[[,Activity,Predecessors,Optimistic,Most Likely,Pessimistic],[\table[[les],[nments]]],[,B,,2,4,6],[,C,A, B,3,4,8],[e Questionnaire,D,C,2,3,7],[E,D,4,6,8],[F,E,5,8,13],[G,E,4,4,4],[H,F, G,2,4,6],[What is the expected duration of the