Question: Table B.1: Information of the activity network. Activity Completion time (days) Activities Duration Preceding Activities Start (ST) 0 A 1 B 2 3 4 D

Table B.1: Information of the activity network.

Table B.1: Information of the activity network. Activity Completion time (days) Activities Duration Preceding Activities Start (ST) 0 A 1 B 2 3 4 D E 5 3 F G B H A I 5 5 2 3 1 J E, F D, G, 1 JH K Finish (FN) 0 a) Draw the SIMPLE activity-on-node diagram for all activities. (* No values) (5 marks) b) Describe the Critical Path (2 marks) c) Compute the values of the Duration, Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF). Suggest - provide your answer in a table format (as below) (18 marks) Suggestion - Write down your answer as the table below Duration ES EF LS LF Activities Start (ST) A B D E F G H J K Finish (FN)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!