Question: ( All answers were generated using 1 , 0 0 0 trials and native Excel functionality. ) At a local university, the Student Commission on
All answers were generated using trials and native Excel functionality.
At a local university, the Student Commission on Programming and Entertainment SCOPE is preparing to host its first music concert of the school year. To successfully produce this music concert, SCOPE has to complete several activities. The following table lists information regarding each activity. An activitys immediate predecessors are the activities that must be completed before the considered activity can begin. The table also lists duration estimates in days for each activity.
ActivityImmediate
PredecessorsMinimum
TimeLikely
TimeMaximum
TimeA: Negotiate contract with selected musiciansB: Reserve siteC: Logistical arrangements for music groupAD: Screen and hire security personnelBE: Advertising and ticketingB, CF: Hire parking staffDG: Arrange concession salesE
The following network illustrates the precedence relationships in the SCOPE project. The project begins with activities A and B which can start immediately time because they have no predecessors. On the other hand, activity E cannot be started until activities B and C are both completed. The project is not complete until all activities are completed.
A network diagram shows the precedence relationship in the project. Activities are labeled from A to G Activities A and B can be started after the start of the project. Activity C can be started after completion of activity A Activity E can be started after comletion of activities C and B Activity G can be started after completion of activity E Activity D can be started after completion of activity B Activity F can be started after completion of activity D The project can be finished after completion of activities F and G
aUsing the triangular distribution to represent the duration of each activity, construct a simulation model to estimate the average amount of time to complete the concert preparations.Round your answers to one decimal place.
Project Duration Average days Standard Deviation days
bWhat is the likelihood that the project will be complete in days or less?Round your answer to the nearest whole number.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock