Question: ( All answers were generated using 1 , 0 0 0 trials and native Excel functionality. ) At a local university, the Student Commission on

(All answers were generated using 1,000 trials and native Excel functionality.)
At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first music concert of the school year. To successfully produce this music concert, SCOPE has to complete several activities. The following table lists information regarding each activity. An activitys immediate predecessors are the activities that must be completed before the considered activity can begin. The table also lists duration estimates (in days) for each activity.
ActivityImmediate
PredecessorsMinimum
TimeLikely
TimeMaximum
TimeA: Negotiate contract with selected musicians569B: Reserve site81215C: Logistical arrangements for music groupA567D: Screen and hire security personnelB333E: Advertising and ticketingB, C159F: Hire parking staffD4710G: Arrange concession salesE3810
The following network illustrates the precedence relationships in the SCOPE project. The project begins with activities A and B, which can start immediately (time 0) because they have no predecessors. On the other hand, activity E cannot be started until activities B and C are both completed. The project is not complete until all activities are completed.
A network diagram shows the precedence relationship in the project. Activities are labeled from A to G. Activities A and B can be started after the start of the project. Activity C can be started after completion of activity A. Activity E can be started after comletion of activities C and B. Activity G can be started after completion of activity E. Activity D can be started after completion of activity B. Activity F can be started after completion of activity D. The project can be finished after completion of activities F and G.
(a)Using the triangular distribution to represent the duration of each activity, construct a simulation model to estimate the average amount of time to complete the concert preparations.Round your answers to one decimal place.
Project Duration Average days Standard Deviation days
(b)What is the likelihood that the project will be complete in 23 days or less?Round your answer to the nearest whole number.
( All answers were generated using 1 , 0 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!