Question: Table below is a time-phased net requirements for Widgets over the next six weeks. Week 1 2 3 4 5 6 Requirements 335 200 140

Table below is a time-phased net requirements for

Table below is a time-phased net requirements for Widgets over the next six weeks. Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 The setup cost is $200 and the holding cost is $0.30 per unit per week. The calculated EOQ is 599 units. Indicate whether you should produce in each of the following weeks Week Produce? 1 No, do not produce 2 [Select] > 3 [Select] 4 [Select] 5 [Select]