Question: table below shows a cost - plus incentive contract. If the client meets the target of R 5 0 million, they will get an incentive

table below shows a cost-plus incentive contract. If the client meets the target of R50 million, they will get an incentive of R6 million. If the costs reach the ceiling of R70 million, the client will receive 2 million. Using this information, fill in the missing letters A TO G shown in the table below. show all calculations. No calculation, no marks. NB: If you cannot write numbers, use words.
NB: if you cannot write numbers, use words
Cost (R Million) Customer pays (R Million) Contractor receives (R Million)
Target (contractor)60 million 6 million (A)
Actual 40 million (B)(C)
actual (D)5 million (E)
actual 75 million (F)(G)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!