Question: table [ [ , Duration / Days , , , , , , , ] , [ Activity , 3 , 6 , 9

\table[[,Duration/Days,,,,,,,],[Activity,3,6,9,12,15,\table[[TOTAL],[PLANNED]],% Completed,Value],[\table[[Landscape],[Design]],2,3,1,,,,100,],[Retaining Wall,,5,3,,,,50,],[Dirt Work,,,4,2,,,33,],[Move Utilities,,,6,4,,,10,],[\table[[Sprinkler],[System]],,,,4,3,,0,],[Planting,,,,,12,,0,],[Planned,2,8,14,10,15,,,],[Cumulative,,,,,,,,],[Actual,2,18,15,17,,,,],[\table[[Actual],[Cumulative]],,,,,,,,]]
Fill out the table
Determine the following Schedule Variances
a., Planned Value =PV
b. Earned Value =EV
c. Schedule Variance = EV-PV
d. Schedule Performance Index =EVPV
e. Estimated Time to Completion SPI
 \table[[,Duration/Days,,,,,,,],[Activity,3,6,9,12,15,\table[[TOTAL],[PLANNED]],% Completed,Value],[\table[[Landscape],[Design]],2,3,1,,,,100,],[Retaining Wall,,5,3,,,,50,],[Dirt Work,,,4,2,,,33,],[Move Utilities,,,6,4,,,10,],[\table[[Sprinkler],[System]],,,,4,3,,0,],[Planting,,,,,12,,0,],[Planned,2,8,14,10,15,,,],[Cumulative,,,,,,,,],[Actual,2,18,15,17,,,,],[\table[[Actual],[Cumulative]],,,,,,,,]] Fill out the table Determine the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!