Question: table [ [ Duration ( Days ) ] , [ Activity , T o , T m , T P , ] , [

\table[[Duration (Days)],[Activity,To,Tm,TP,],[A,4,6,9,],[D,6,10,15,],[G,7,11,15,],[H,10,20,36,],[M,8,10,14,],[O,4,5,8,]]
The critical path has five activities in a CPM network. their durations are tabulated next. Find:
I) The duration of the project with its standard deviation
The probability that the project will be finished by the end of day 65
The probability that the project will finish before day 60
The probability that the project will finish on the 62nd day
The probability that the project will finish at least six days early
The completion date with at least a 95% confidence level
\ table [ [ Duration ( Days ) ] , [ Activity , T

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!