Question: table [ [ Duration ( Days ) ] , [ Activity , T o , T m , T P , ] , [
tableDuration DaysActivityADGHMO
The critical path has five activities in a CPM network. their durations are tabulated next. Find:
I The duration of the project with its standard deviation
The probability that the project will be finished by the end of day
The probability that the project will finish before day
The probability that the project will finish on the nd day
The probability that the project will finish at least six days early
The completion date with at least a confidence level