Question: table [ [ H , D , E , 1 3 , $ 1 3 0 0 , 1 1 , $ 2 4

\table[[H,D,E,13,$1300,11,$2440,Your last answer was interpreted as follows: 570],[],[I,F,H,19,$1710,16,$2850,Your last answer was interpreted as follows: 380],[J,F, G,18,$2160,15,$3630,490,],[Your last answer was interpreted as follows: 490]]
In the table below enter the best choice for each crash. Each line represents 1 day only. If you want to crash the same activity(ies) for 2 or more days in a row then you should repeat it (them) in as many lines as necessary. Answers should be in upper case. If you wish to crash more than one activity then they should be written with + signs and no spaces. For example A+B if you want to crash A and B at the same time or A+B+C if you want to crash the three activities at the same time.
\table[[Project Duration,Activities to crash,Direct Cost,Indirect Cost,Total Cost],[58,None,,,],[57,,,,],[56,,,,],[55,,,,],[54,,,,]]
Note: It may be possible to crash your project more than 4 days, but you are only expected to crash it 4 days.
For each duration enter the direct, indirect and total cost assuming that indirect costs are $295 per day.
 \table[[H,D,E,13,$1300,11,$2440,Your last answer was interpreted as follows: 570],[],[I,F,H,19,$1710,16,$2850,Your last answer was

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!