Question: table [ [ ID , Activity,Predecessor ( s ) , Duration ( days ) ] , [ A , Clear site, - , 1
tableIDActivity,Predecessor sDuration daysAClear site,BBring utilities to site,CExcavate,ADPour foundation,CEOutside plumbing,B CFFrame house,DGDo electric wiring,FHLay floor,FILay roof,E HJInside plumbing,I,KShingling,F JLOutside sheathing insulation,FMInstall windows and outside doors,G JNDo brick work,OOInsulate walls and ceiling,I, PPCover walls and ceiling,PQInsulate roof,I, NRFinish interior,SFinish exterior,,TLandscape,,
The activities in the following table describe the construction of a new house. Draw the correct diagram!