Question: table [ [ Item , Activity,Activity Description, table [ [ Duration ] , [ ( Days ) ] ] , table [
tableItemActivity,Activity Description,tableDurationDaystablePredecessorsALot preparation,tableClear trees, clear stumps,rough grading, excavateNoneBFoundation,tableFrame and pour footing,install forms, pour wallsACFrame floor system,tableInstall carrying wall, joists,sheathingBFrame exterior walls,tableFrame exterior walls andsheathing install interiorpartitions level oneCtableFrame second level floorsystemInstall joists, sheathing,DtableFrame second levelexteriortableFrame exterior walls andsheathing install interiorpartitions level twoEOpen the Activity List, Figure insert the CPM "Node" template' in each position to outline the CPM Diagram of the "Build a House" project. Then, using the "Insert" feature, along with arrow shapes from the "Shapes" option, connect your node circles to indicate the paths that you have determined represent the project. Remember to label the centre bar to identify each activity and its duration. Remember to refer to the Activity List
Next, complete Forward Pass through the diagram to calculate the ES and EF values for each activity. In your diagram, make note of those values in the appropriate location.
Once you have completed the Forward Pass, then complete Backward Pass. The backward pass will provide the Latest Finish nd Latest Start information for each activity.
Calculate Slack Time to determine the Critical Path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock