Question: table [ [ Module 3 , Line Balancing Exercise,SCM 3 0 0 ] ] AZ Devices manufactures a number of different electronic devices. One

\table[[Module 3,Line Balancing Exercise,SCM 300]]
AZ Devices manufactures a number of different electronic devices. One of their products is AZ-750 calculator. Calculators are sold every day of the month, but are only produced at the factory 5 days per week, Monday through Friday.
Their monthly demand for these calculators is 8140. The factory is open 8 hours per day. Assume an average of 22 working days per month in the factory. You will be using daily demand, so use this information to calculate the daily demand.
LINE BALANCING - PRECEDENCE DIAGRAM
Remember, the factory is open 22 days per month. The assembly line runs 8 hours per day. The following precedence diagram gives the necessary data to answer the line balancing related questions that follow.
LINE BALANCING - PROBLEMS
Question #1-Make sure this answer is correct before moving on. What is the CYCLE TIME that ensures the desired output rate?
(NOTE: NEVER ROUND-UP YOUR CYCLE TIMEI!! You should be able to figure out why this should never be done. Think about it.)
 \table[[Module 3,Line Balancing Exercise,SCM 300]] AZ Devices manufactures a number of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!