Question: Cycle time= 77 Question #2 What is the theoretical minimum number of workstations? Group of answer choices 12 11 7 10 5 6 13 9

Cycle time= 77 Question #2 What is the

Cycle time= 77

Question #2

What is the theoretical minimum number of workstations?

Group of answer choices

12

11

7

10

5

6

13

9

8

Question #3

If someone were to create an assembly line that had the theoretical number of workstations, what would the efficiency of that assembly line be?

Group of answer choices

0.959

0.872

0.852

0.697

0.996

0.814

0.741

0.828

0.916

Question #4

If someone were to create an assembly line that had the theoretical number of workstations, what would the total amount of idle in that assembly line?

Group of answer choices

79

87

2

233

161

84

156

238

7

Question #5

If someone were to create an assembly line that had 10 workstations, what would the efficiency of that assembly line be?

Group of answer choices

0.916

0.697

0.959

0.852

0.775

0.828

0.741

0.872

0.736

0.814

Question #6

If someone were to create an assembly line that had 10 workstations, what would the total amount of idle in that assembly line?

Group of answer choices

233

2

87

79

84

238

7

161

156

Need help with 1-6! Please and thankyou

Module 3 Line Balancing Exercise SCM 300 AZ Devices manufactures a number of different electronic devices. One of their products is AZ-750 calculator. Calculators are sold every day of the month, but are only produced at the factory 5 days per week, Monday through Friday. Their monthly demand for these calculators is 8140. The factory is open 8 hours per day. Assume an average of 22 working days per month in the factory. You will be using daily demand, so use this information to calculate the daily demand. LINE BALANCING - PRECEDENCE DIAGRAM Remember, the factory is open 22 days per month. The assembly line runs 8 hours per day. The following precedence diagram gives the necessary data to answer the line balancing related questions that follow. 17 A 61 71 G N 10 D 50 1 60 M 9 B 33 28 59 L 51 27 32 29 E F H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!