Question: Table of Crashing Decision table [ [ , TIME ( WEEKS ) , COST ( $ ) ] , [ ACTIVITY , IMMEDIATE,NORMAL,CRASH,NORMAL,CRASH ]

Table of Crashing Decision
\table[[,TIME (WEEKS),COST ($)],[ACTIVITY,IMMEDIATE,NORMAL,CRASH,NORMAL,CRASH],[P,cdots,3,2,3,000,3,300],[B,cdots,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]]
Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,
Using Table of Crashing Decision, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?
Activity H
Activity J
Activity B
Activity E
 Table of Crashing Decision \table[[,TIME (WEEKS),COST ($)],[ACTIVITY,IMMEDIATE,NORMAL,CRASH,NORMAL,CRASH],[P,cdots,3,2,3,000,3,300],[B,cdots,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]] Since no indirect cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!