Question: The following table shows the activities for a project. TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSOR(S) NORMAL CRASH NORMAL CRASH AVAILABLE WEEKS OF CRASHING CRASHING

  1. The following table shows the activities for a project.

TIME (WEEKS)

COST ($)

ACTIVITY

IMMEDIATE PREDECESSOR(S)

NORMAL

CRASH

NORMAL

CRASH

AVAILABLE WEEKS OF CRASHING

CRASHING COST / WEEK

A

Start

3

2

3,000

3,300

B

Start

6

4

8,000

9,000

C

A

1

1

4,000

4,000

D

A

5

4

3,500

4,000

E

B

4

3

4,750

5,500

F

C

2

2

2,000

2,000

G

D

1

1

4,000

4,000

H

D,F

3

2

3,500

3,750

I

E,G

3

2

3,000

4,250

J

E

2

1

5,000

7,000

Finish

H, I, J

--

--

--

--

    1. Draw the network diagram.
    2. What is the critical path for the project using the normal time?
    3. Complete the table by filling the missing information.
    4. How many week(s) of crashing are available for activity E?
    5. Which activity should be crashed first?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!