Question: table [ [ Project Duration,Direct costs,Indirect costs,Total Costs ] , [ 2 5 , 4 5 0 , 4 5 0 , 9 0

\table[[Project Duration,Direct costs,Indirect costs,Total Costs],[25,450,450,900],[24,475,325,800],[23,495,350,845],[22,525,265,790],[21,610,*225,835]]
Which project time unit is considered the optimum cost-time duration?
 \table[[Project Duration,Direct costs,Indirect costs,Total Costs],[25,450,450,900],[24,475,325,800],[23,495,350,845],[22,525,265,790],[21,610,*225,835]] Which project time unit is considered