Question: Table Q1 shows the logic table for a particular project. Activity Precedence Time (days) A Start 3 B A 2 3 D A 5 E

Table Q1 shows the logic table for a particular

Table Q1 shows the logic table for a particular project. Activity Precedence Time (days) A Start 3 B A 2 3 D A 5 E B 2 F B 5 G E 2 H C,F 3 I D.H 1 J I,G 1 Table Q1 a. Construct a Network Diagram showing the various logical activity relationships from this information. Perform a forward and backward pass to complete activity boxes (i.e. early start, early finish, late start, late finish, float, duration). (15 marks) b. Highlight the critical path on your diagram. (10 marks)