Question: table [ [ Task , Length,Dependency ] , [ a . Write and agree on contracts, 3 weeks, ] , [ b . Secure
tableTaskLength,Dependencya Write and agree on contracts, weeks,b Secure financing, weeks,ac Obtain permits, weeks,a bd Site work, weeks,a b ce Build foundation, weeks,b c df Erect walls, weeks,d eg Build roof, weeks,fh Rough in plumbing, weeks,fi Rough in electrical, weeks,fj Rough in furnace and air conditioning, week,fk Finish exterior, weeks,f g iI Finish interior, weeks,f g h i jm Finish plumbing, weeks,h in Finish electrical, week,i Io Finish furnace and air conditioning, day,j Ip Wait for inspection, weeks,k l m n o
If the project proceeds on schedule, how much time should have elapsed before the roof is built? If appropriate, give a range of time.
Roof building should begin after
weeks and should end after
weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
