Question: table [ [ Task , Length,Dependency ] , [ a . Write and agree on contracts, 3 weeks, ] , [ b . Secure

\table[[Task,Length,Dependency],[a. Write and agree on contracts,3 weeks,],[b. Secure financing,4 weeks,a],[c. Obtain permits,7 weeks,a, b],[d. Site work,4 weeks,a, b, c],[e. Build foundation,3 weeks,b, c, d],[f. Erect walls,4 weeks,d, e],[g. Build roof,5 weeks,f],[h. Rough in plumbing,2 weeks,f],[i. Rough in electrical,2 weeks,f],[j. Rough in furnace and air conditioning,1 week,f],[k. Finish exterior,6 weeks,f, g, i],[I. Finish interior,6 weeks,f, g, h, i, j],[m. Finish plumbing,2 weeks,h, i],[n. Finish electrical,1 week,i, I],[o. Finish furnace and air conditioning,1 day,j, I],[p. Wait for inspection,2 weeks,k, l, m, n, o]]
If the project proceeds on schedule, how much time should have elapsed before the roof is built? If appropriate, give a range of time.
Roof building should begin after
weeks and should end after
weeks.
 \table[[Task,Length,Dependency],[a. Write and agree on contracts,3 weeks,],[b. Secure financing,4 weeks,a],[c. Obtain

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!