Question: table [ [ Task , table [ [ Duration ] , [ ( months ) ] ] , Predecessors ] , [ A ,
tableTasktableDurationmonthsPredecessorsANoneBACADBECFDGD EHF G
Using the project schedule above, draw a precedence network diagram; determine the critical path duration and the float on the critical path.