Question: table [ [ Task , table [ [ Duration ] , [ ( months ) ] ] , Predecessors ] , [ A ,

table[[Task,\table[[Duration],[(months)]],Predecessors],[A,2,None],[B,5,A],[C,4,A],[D,3,B],[E,2,C],[F,6,D],[G,8,D, E],[H,4,F, G]]
Using the project schedule above, draw a precedence network diagram; determine the critical path duration and the float on the critical path.
 table[[Task,\table[[Duration],[(months)]],Predecessors],[A,2,None],[B,5,A],[C,4,A],[D,3,B],[E,2,C],[F,6,D],[G,8,D, E],[H,4,F, G]] Using the project schedule above, draw a precedence