Question: The activities, durations, and precedence relations for a project are provided below. Activity A: Duration is 3 months. Predecessor(s): None. Activity B: Duration is 1
The activities, durations, and precedence relations for a project are provided below.
Activity A: Duration is 3 months. Predecessor(s): None.
Activity B: Duration is 1 month. Predecessor(s): None.
Activity C: Duration is 2 months. Predecessor(s): None.
Activity D: Duration is 2 months. Predecessor(s): A,B
Activity E: Duration is 4 months. Predecessor(s): B.C.
Activity F: Duration is 2 months. Predecessor(s):D,E.
Question C.1: Which of the following is/are a critical path/paths of the project?
A Start-A-D-F-End
B Start-B-D-F-End
C Start-A-B-C-D-E-F-End
D Start-C-E-F-End
E Start-B-E-F-End.Start-C-E-F-End,Start-B-D-F-End
Question C.2: Which Activity, if delayed, will extend the duration of the project?
A
B
C
D
None of Above