Question: table [ ] The work schedule is based on a 5 - days week plan. As part of your management process, you evaluated the

\table[]
The work schedule is based on a 5-days week plan. As part of your management process, you evaluated the progress of the project at the end of week 6, and found the following results:
\table[[Name,Activity,Percentage Completion,Actual Cost ($)],[A,Visit Plant,100,1200],[B,Gather information,100,1800],[C,Analyze Data,100,1900],[D,Brainstorm Solution,75,4000],[E,Select Solution,25,700],[F,Present to Client,0,-],[G,Revise Solution,0,-],[H,Get approval Client,0,],[I,Implement Program,0,],[J,Closing Project,0,]]
 \table[] The work schedule is based on a 5-days week plan.