Question: table [ [ WBS , Person A ( hours ) , table [ [ Person B ] , [ ( hours ) ]

\table[[WBS,Person A (hours),\table[[Person B],[(hours)]],\table[[Sub - Contractor],[($)]],Materials ($)],[1.1,,10,,1000],[1.2,5,10,5000,],[1.3,20,20,,],[2.1,,5,2500,2500],[2.2,15,,,2500],[3.1,15,10,10000,2500],[3.2,10,10,,2500]] Suppose the project start on 1 st of January 2012, with an opening balance of
$1000. Project construction activities are scheduled 1.1-1.3 in January, 2.1-2.2 in
February and 3.1-3.2 in March. The labour cost is paid in the month of use, material has
a one month credit, and the sub-contractor cost has a one month credit. Develop the
project cash flow statement from January to April 2012. The income will be based on a
monthly progress payment of previous month.Ouestion 44.
[25 Marks]
a) Given the following sets of information, work out the labour rate for an average
mointh.
b) Person A and B will be employed to carry out a project with seven (7) activities. Given
the following information, calculate the estimates charges fro each individual activity, the
cumulative charges for work package 1,2, and 3, and finally the total estimate of charge. A 20%
profit on all sub-contractors and procurement cost is added to all jobs. Suppose the contractor is
\ table [ [ WBS , Person A ( hours ) , \ table [

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!