Question: table [ [ What are the critical activities?,A , B , C , E , H , I, ] , [ What is the

\table[[What are the critical activities?,A, B, C, E, H, I,],[What is the slack for C ?,0,],[What is the slack for D?,3.,],[What is the slack for E?,0,],[What is the slack for F?,0,],[What is the length of the project?,15,time periods.]]
You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project network that follows, complete the
forward and backward pass, compute activity slack, and identify the critical path.
 \table[[What are the critical activities?,A, B, C, E, H, I,],[What is