Question: TABLE/PERT: For the Activity Table below: a. Draw the PERT with earliest and latest start and finish times per activity. b. List all Network Paths
TABLE/PERT: For the Activity Table below:
a. Draw the PERT with earliest and latest start and finish times per activity.
b. List all Network Paths
c. Determine the slack time for each activity
d. Show the Critical Path (CP)
e. Determine the minimum time to project completion
f. What is the Pessimistic and Optimistic time for 80 percent Confidence Interval for the project (use CP time as "realistic") (sigma -project = 0.5)
g. Make a staffing table for both a forward and backward analysis. 