Question: Takt time is the cycle time needed in a production system to match the pace of production to the demand rate and is used in

Takt time is the cycle time needed in a

Takt time is the cycle time needed in a production system to match the pace of production to the demand rate and is used in Lean Production systems for line balancing. Given the following data, what is the takt time per shift? Total time per shift is 480 minutes. There are two 15 minute breaks and one 30 minute lunch. Daily demand is 160 units. a. 1.000 minutes per cycle b. 2.625 minutes per cycle c. 2.813 minutes per cycle d. 2.906 minutes per cycle e. 3.000 minutes per cycle