Question: Tas ks ID Task Name Duration Predecesso rs - Training Rollout Initiative and Plan ( TRIP ) - TRIP - Stage 1 - Project Planning

Tas ks
ID Task Name Duration Predecesso
rs
- Training Rollout Initiative and Plan (TRIP)
- TRIP - Stage 1- Project Planning
A Define project objectives and describe mission statement 10 days -
B Ensure total participation by training team support staff 5 days -
- Identify Departments or End-User Community to be Trained
C Create list of target departments 5 days A
D Perform departmental training needs analysis 35 days B,C
E Compile results and present findings to training coordinator 10 days D
F Prioritize training delivery according to critical need 10 days E
G Inform department heads of the training initiative 10 days C
H Determine if training can be done in-house or outsourced 8 days C
- Seek Input from Training Vendor
I Define vendor deliverables - can they meet our needs? 5 days H
J Obtain vendor commitment to training rollout schedule 15 days G,I
K Review and customise training material 35 days J
L Obtain approval for purchase orders to cover vendor invoices 20 days K
- Perform End-User Skill Assessment
M Create a list of training recipients by department 10 days F
N Send skill assessment forms to department heads 10 days G,M
O Collect and compile results by department 25 days N
P Initiate end-user placement matrix 15 days O
Q Finalize project budget 10 days O
R Stage 1- TRIP - End project initiation 1 days L,P,Q
2) Calculate Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Total Float (TF) for each task.
3) What is the total duration of the Stage 1 of this project?
4) Identify and show the Critical Path for the stage 1
Question 1B
One of your team members working on the Task Review and customise training material has just had a baby and would need to go on maternity leave, a suitable maternity cover will not resume earlier than a month. The project has been struggling with limited resources, hence, the delivery of this Task would be delayed by 40 working days.
Determine the impacts this would have on your schedule.
pls give answer and calculation for each task and update calculation as per delay in 1B . please answer in detail subject is project mangemnt

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!