Question: Tas ks ID Task Name Duration Predecesso rs - Training Rollout Initiative and Plan ( TRIP ) - TRIP - Stage 1 - Project Planning
Tas ks
ID Task Name Duration Predecesso
rs
Training Rollout Initiative and Plan TRIP
TRIP Stage Project Planning
A Define project objectives and describe mission statement days
B Ensure total participation by training team support staff days
Identify Departments or EndUser Community to be Trained
C Create list of target departments days A
D Perform departmental training needs analysis days BC
E Compile results and present findings to training coordinator days D
F Prioritize training delivery according to critical need days E
G Inform department heads of the training initiative days C
H Determine if training can be done inhouse or outsourced days C
Seek Input from Training Vendor
I Define vendor deliverables can they meet our needs? days H
J Obtain vendor commitment to training rollout schedule days GI
K Review and customise training material days J
L Obtain approval for purchase orders to cover vendor invoices days K
Perform EndUser Skill Assessment
M Create a list of training recipients by department days F
N Send skill assessment forms to department heads days GM
O Collect and compile results by department days N
P Initiate enduser placement matrix days O
Q Finalize project budget days O
R Stage TRIP End project initiation days LPQ
Calculate Early Start ES Early Finish EF Late Start LS Late Finish LF and Total Float TF for each task.
What is the total duration of the Stage of this project?
Identify and show the Critical Path for the stage
Question B
One of your team members working on the Task Review and customise training material has just had a baby and would need to go on maternity leave, a suitable maternity cover will not resume earlier than a month. The project has been struggling with limited resources, hence, the delivery of this Task would be delayed by working days.
Determine the impacts this would have on your schedule.
pls give answer and calculation for each task and update calculation as per delay in B please answer in detail subject is project mangemnt
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock