Question: Task A takes 25 days and can begin as soon as the project starts. Task B needs to be done after the completion of Task
Task A takes 25 days and can begin as soon as the project starts. Task B needs to be done after the completion of Task A and takes an estimated 20 days. Task C can start when Task B starts and takes an estimated 30 days. Task D can start as soon as Task B is complete and will take at least 10 days to complete. Task E can start as soon as tasks C and D are completed and takes 40 days to complete. What is the duration of the critical path? 95 45 55 0