Question: Task C is directly preceded by two tasks: Task A and Task B. Task A has an expected task completion time of five weeks and

Task C is directly preceded by two tasks: Task A
Task C is directly preceded by two tasks: Task A and Task B. Task A has an expected task completion time of five weeks and an ES time of Week 6. Task B has an expected task completion time of seven weeks and an ES time of Week 7. Task C has an expected task completion time of 10 weeks. The EF for activity C is week 24. 12. 14 7